Work progressing on Wakonda cafe

Work progressing on Wakonda cafe Ten weekends plus some additional days have gone into the building of the Wakonda Community Cafe. Most of the work has been accomplished as the result of dedicated loyal community volunteers.

As of this writing the drop-in ceiling with recessed lighting has been completed and the subfloor has been installed. The painting has been completed, the furnace is installed and operational and much of the initial plumbing completed.

On the schedule is the laying of the floor tile, the installing of the hood in the kitchen and the appliances. Some of the equipment and fixtures have already been purchased.

Within a few weeks we should be looking at setting a time for opening.