Life will be Sweet on Cherry Street

Work this week:

• Gravel base course Cottage Avenue to Dakota Street.

• Traffic switched to south side, west end to service road.

• Removals, excavation north side, west end to service road.

• Curb and gutter Cottage Avenue to Dakota Street.

Planned for next week:

• Limited access to driveways west of Highway 19.

• Paving from Cottage Avenue to Dakota Avenue.

• Street lights from Cottage Avenue to Highway 19.

• Removals, excavation north side, west end to service road.

Miscellaneous:

• Public project meetings are now bi-weekly. The next public and contractor meetings are Wednesday, Sept. 16 and 30 and will be held at 10 a.m. at the Vermillion Hy-Vee café.

• Speed limit is 20 mph and no parking through the temporary detour. Speeding and parking violations will continue to be issued during the construction season by the Vermillion Police Department. Cars parked in no parking areas will be towed.

• DO NOT add, remove or relocate barrels, barricades, signs, temporary business signs, etc. on the construction sight. If concerns arise, please contact D&G Concrete Construction or the DOT for evaluation.

• Upgrades on construction progress and changes will be available on our Web site dgconcrete.com.

Bookmark the permalink.

Leave a Reply

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>