Workers from D&G Concrete Construction, Inc. and other contractors completed the following work on the Cherry Street reconstruction project from April 28-May 2.
Sanitary sewer main complete from Jefferson Street to Plum Street.
Removals from Jefferson Street to 150 feet east of Plum Street complete.
Qwest working on relocating phone lines, expect completion May 6.
Removals, undercut and fill on turn lane Highway 19 South continuing.
Storm sewer work from Jefferson Street to Plum Street.
Work planned for May 5-May 9:
Sanitary sewer services Jefferson Street to Plum Street.
Continue fill on turn lane Highway 19 South.
Water main and storm sewer from Jefferson Street to Norbeck Street.
Removals from Norbeck Street to east project limit. Miscellaneous:
Speed limit is 25 mph through the construction project. Speeding violations are and will continue to be issued during the construction season by the Vermillion Police Department.
Do not add, remove or relocate barrels, barricades, signs, temporary business signs, etc. on the construction site. If concerns arise, please contact D&G Concrete Construction or the DOT for evaluation.
Temporary driveways are being constructed. If anyone has any concerns about the driveway or problems with semi deliveries, please contact the DOT and other arrangements can be discussed.
No parking on Princeton Street from Cherry Street to the Pamida entrance.
Updates on construction progress and changes will be available online at dgconcrete.com.